Assessing Risk on Warehouse Automation Projects

By Ian Hobkirk | 09/10/2019 | 5:04 AM

Most companies that have attempted to implement automated material handling equipment have discovered that these projects can be particularly vulnerable to Murphy’s Law, the principal that, “anything that can go wrong, will go wrong.” This blog is third in an ongoing series on “Beating Murphy’s Law in Warehouse Automation Projects.”

Blog 3 DC350
A good first step towards accounting for Murphy’s Curve is to perform a risk assessment on each of the potential solution scenarios being considered. Often, the technology that holds the greatest promise of cost savings can also involve the greatest risk of failure. Certain forms of warehouse automation may be very unforgiving of minor design flaws or changing business conditions, while other technologies may be more flexible and adaptable to these forms of change. Other technologies may seem promising but may be relatively new and untested in the marketplace. Companies seeking aggressive cost savings can often be blind to the risks inherent in some technologies. A thorough risk assessment can be an effective way to highlight these risks and impact the choice of design and technology early in the project.

To perform a risk assessment, start by identifying the specific risks which are present on the project. Examples of risks to account for include:

Risk bullet@2x

Next, assign each risk a weight factor based upon your company’s tolerance for risk in this area. For example, the company may be relatively unconcerned with the risk of cost overruns compared to the risk of the project not going live on time prior to a peak demand period. These two risks should be weighted differently.

Lastly, give each potential solution scenario a numeric rating for each of the risk areas (a low score represents low risk, a high score represents high risk). Multiply this rating by the weighting factor to achieve a weighted risk score for each solution scenario. It may be discovered that certain solutions that offer the highest potential for labor savings may also have the highest risk of cost or schedule overruns. As a result, the company may choose a solution that is less automated, but less risky, or may choose to proceed with the riskier technology and build in contingency factors for cost and time overruns. 

 

 

Comments

bbb

By submitting your comments, you agree to our Terms of Service.

The opinions expressed herein are those solely of the participants, and do not necessarily represent the views of Agile Business Media, LLC., its properties or its employees.

About Ian Hobkirk

Ian Hobkirk

Ian Hobkirk is the founder and Managing Director of Commonwealth Supply Chain Advisors. Over his 20-year career, he has helped hundreds of companies reduce their distribution labor costs, improve space utilization, and meet their customer service objectives. He has formed supply chain consulting organizations for two different systems integration firms, and managed the supply chain execution practice at The AberdeenGroup, a leading technology analyst firm.



Categories

Popular Tags

Recent Comments

Subscribe to DC Velocity

Subscribe to DC Velocity Start your FREE subscription to DC Velocity!

Subscribe to DC Velocity
Renew
Go digital
International